DueVault · California · public projects
California prompt payment interest calculator
On a California public project, a prime contractor must pay its subcontractors within 7 calendar days of being paid. Miss that and interest runs at 2% per month — under Cal. Bus. & Prof. Code § 7108.5.
The rule in California
- Agency to prime contractor
- 30 days after a payment request; 60 days of completion for final.
- Prime contractor to subcontractor
- 7 calendar days after the prime is paid.
- Interest when that is missed
- 2% per month
Exceptions worth knowing before you rely on a number
- The 7-day deadline applies “unless otherwise agreed to in writing” — your subcontract can change it.
- Where there is a good faith dispute, the paying party may withhold up to 150% of the disputed amount.
- §7108.5 covers public and private work EXCEPT where Public Contract Code §10262 applies (certain state projects).
- 10% per year is the rate owed to primes; 2% per month is the subcontractor rate.
Statute read 2026-08-28 from the published text. DueVault is not a law firm and this is not legal advice. Public construction only.